Evans Construction is currently building a new sidewalk on the north side of Hansen Ave from Cache St to Redmond St. This week, Evans will install irrigation sleeves, driveway aprons, subgrade, curb & gutter, and sidewalk along Hansen from Cache to King, and light bases from Cache to Willow. Weather and work progress permitting throughout the week, Evans may also begin to install subgrade for the sidewalk from King to Willow. During this time, the street will be closed to through traffic and open only to pedestrian and local traffic. However, the intersection at King will remain open through the week.