Hansen Ave between Cache St and Willow St may be closed during the day this week. Evans Construction is building a new sidewalk on the north side of Hansen Ave from Cache St to Redmond St.  The week of July 27-31, Evans will install concrete driveway aprons and sidewalk along Hansen from King to Willow, buried power and subgrade along Hansen from Willow St east to 315 Hansen, and a tree removal at 235 Hansen. While the street is closed to through vehicular traffic, it remains open for pedestrians and some local access. Motorists are advised to watch for closure and directional signs.